The works, part of Renfe Viajeros's Plan A Punto, are estimated to last four and a half months. The project will be carried out in several phases, starting with preparatory tasks such as installing auxiliary elements and fencing off work areas.
The main phase, lasting approximately three months, will include the renovation and reorganization of the parking lot, improvements to pedestrian routes and accessibility, sanitation and drainage work, and lighting upgrades. Interventions on trees and garden areas are also planned.
The final phase, lasting about a month, will focus on finishing touches, horizontal and vertical signage, painting, and the removal of temporary facilities, after which the parking lot will reopen.
Key actions include renewing the parking lot's paving, reordering parking spaces and internal lanes, improving pedestrian paths and accessibility, repairing sanitation and drainage systems, and enhancing lighting. The total number of parking spaces will be maintained, including designated spots for people with reduced mobility.
During the construction, the parking lot will be progressively affected, with delimited and restricted areas. Access to the Cercanías station remains operational, although routes may be temporarily modified. No specific alternative parking has been provided, so drivers will need to use available spaces in the vicinity.