Third lane works on M-607 between Tres Cantos and Colmenar Viejo advance

The Community of Madrid is extending the highway by 14.6 kilometers to improve capacity and reduce congestion, with sections already open and completion expected in 2027.

Generic image of a highway under construction in a Mediterranean landscape.
AI

Generic image of a highway under construction in a Mediterranean landscape.

The Community of Madrid has made progress on the expansion works of the M-607, which include adding a third lane in each direction between Tres Cantos and Colmenar Viejo. The Minister José María García Gómez visited the project, covering 14.6 kilometers.

The first section of this expansion was opened to traffic in April, and the second in November. This latter section, now operational up to kilometer marker 26.700, runs between Tres Cantos Norte and the southern bypass of Colmenar Viejo, connecting with the M-618. Projections indicate the extension will reach kilometer 29 in the early months of 2027 and kilometer 30.3 later that same year.
The final kilometer of the project will feature an overpass for fauna, measuring 60 meters wide and 140 meters long, scheduled for completion in the second quarter of next year. This structure will include four false tunnels covered with vegetation to encourage the growth of native plants and allow animals to cross safely above the roadway.
During the construction, normal traffic flow is maintained on the M-607, which handles over 63,000 vehicles daily. Additionally, the cycle path connecting Colmenar Viejo with the capital remains open.
The expansion of this road, one of the regional routes with the highest traffic intensity alongside the M-501 and M-45, aims to increase the road's capacity, reduce peak-hour congestion, and improve safety and visibility at various points along the route.
Based on information from the official source: Comunidad de Madrid — Notas de prensa (23/11/2026)